TDI is committed to making the development of this project open and transparent for regulators and citizens alike. This page contains an outline of the development schedule TDI intends to pursue.
With any project of this magnitude, there are multiple levels of review at the state and federal levels, and the outline below is subject to change. Please check back periodically for updates.
Winter 2010
- Presidential Permit application filed with U.S. Department of Energy
- Initial Article VII filing with New York State Public Service Commission
- Federal NEPA review process begins
- First public meetings along the route
- Applications filed with U.S. Army Corps of Engineers
- Final Article VII application filed with the NYS PSC
- Draft Environmental Impact Statement (EIS) completed
- Public comment on U.S. Army Corps of Engineer permit applications
- Public Hearings on Article VII application
- Public comments on Draft EIS
- Application review in New York and Connecticut
- Final Environmental Impact Statement completed
- Presidential Permit issued
- Article VII permit granted
- U.S. Army Corps of Engineers permits issued
- New York State Water Quality Certificate issued
- Commencement of construction of upland facilities
- Commencement of cable manufacture and/or installation